Here is the Outlook for the High Street Improvements Project for anticipated and projected work from September 25th - September 29th.
There will be construction near the intersection of Route 1 (Lafayette Road) and High Street in the area between Dearborn Avenue and Academy Avenue. East bound traffic on High Street at the intersection will be detoured to Winnacunnet Road. Access to Dearborn Avenue may be limited while construction occurs at the intersection of Dearborn Avenue and High Street.
Buses will be able to get through AND BUSINESSES ARE OPEN!
USE THE HIGH STREET PARKING LOT.


As with any construction project, weather, unexpected delays or field conditions may change this schedule.
Anticipated Work for the week of September 25, 2023
- Crew 1
- Monday - Thursday: Work will include sewer main installation on High Street from Dearborn Avenue to Academy Avenue.
- Friday: Sewer main paving on High Street between Dearborn Avenue and Academy Avenue.
- Crew 2:
- Monday - Thursday: Work will include drainage and sewer service installation between Moulton Road and Mill Road.
- Friday: Drainage and sewer service paving on High Street between Moulton Road and Mill Road.